Mittelplate
Requirement
tunnelling project
| Employment | Oil, Water | |
|---|---|---|
| Geology | sand | |
| Tunnel Length | 7,500 m | |
| Diameter | 406 mm |
Solution
machine data
| Machine Type | HDD-Rig | |
|---|---|---|
| Support Techniques | Horizontal Directional Drilling | |
| Cutterhead Power | 200 kW | |
| Torque | 120 kNm, 90 kNm |
Germany's largest oilfield is in the North Sea where the black gold is pumped up by the Mittelplate drilling platform. To create a better connection to the mainland at Schleswig-Holstein, an oil and a water pipeline were to be laid between Mittelplate and the Dieksand land station.
The construction work presented typical marine obstacles for man and machine: tides, rough waters with wind speeds of up to 75 kilometers per hour and severe erosion because of the salty sea air.
Two HDD Rigs drilled the way for the two pipelines. The horizontal drilling work was completed in mid May 2005, one month earlier than expected. In only two months, 7,500 meters of pipeline were laid. On conclusion of the project, an oil and a water pipeline now connect the Mittelplate drilling platform with the Dieksand land station.