SuedLink is one of the key grid expansion projects for the energy transition in Germany. In future, the ultra-high-voltage direct current transmission line will transport electricity around 700 kilometers from the wind power regions in the north to the industrial centers in southern Germany. A key section of the project is the approximately 5.2 kilometer long crossing beneath the Elbe between Wewelsfleth in Schleswig-Holstein and Wischhafen in Lower Saxony.
Working for grid operator TenneT, the ARGE Tunnel ElbX consortium of PORR and Wayss & Freytag Ingenieurbau AG is building this tunnel, which will house six 525 kV cables as well as the necessary control, safety and monitoring technology. Rail tracks for maintenance and service vehicles are also being installed. The project is representative of more than 4,500 crossings that will be necessary in Germany alone as part of grid expansion.
To make sure tunnel boring machine Elsa can break through at the target shaft near Wischhafen as planned, the Herrenknecht engineers worked closely with their colleagues from contractors PORR and Wayss & Freytag Ingenieurbau AG to develop a machine you don't see every day. It must overcome both very sticky Lauenburg clay and various abrasive sands and gravels on the geologically very heterogeneous tunnelling section. "The challenge was to accommodate the technology of the highly complex Mixshield in a machine with a diameter of just under 5 meters," says Johannes Faisst, Senior Project Manager Traffic Tunnelling at Herrenknecht. The 190 meter long Mixshield with a diameter of 4.9 meters is designed for variable and complex geologies consisting of clay, tidal mud deposits, peat, sand and gravel, as well as for high water pressure of up to 3.8 bar beneath the Elbe River. A multiple sealing system reliably protects the machine from water ingress at a depth of around 20 meters. At the same time, precast concrete elements are installed during the drive to permanently line the tunnel.
The fully assembled machine has been underway since early 2025. On November 16, 2025, the ARGE Tunnel ElbX consortium tunnelling crews had already excavated 2,600 meters of tunnel, half the total length, and celebrated the so-called "Bergfest" marking the halfway point.