São Paulo Metro Line 5
Brazil, São Paulo
2013 – 2016

Since São Paulo's metro Line 1 was commissioned in 1974 the network in the city of 21 million has gradually been expanded. After Lines 2 and 3, from 2004 the new Line 4 was built and commissioned in 2010. Between 2007 and 2009 the Herrenknecht EPB Shield S-336 was used for this.

In the southwest of São Paulo runs Line 5, which is being extended as far as the city center and is to be connected to the rest of the metro network. The extension is being built partly as a single-tube double-track tunnel and partly as a twin-tube single-track tunnel.

The EPB Shield that proved itself in the construction of Line 4 was refurbished for Line 5 by the local Herrenknecht subsidiary in Brazil in cooperation with the specialists from Schwanau. The diameter was enlarged by about a meter to 10.54 meters so it could excavate the double-track sections. Two other EPB Shields with a smaller diameter (6,860 mm) were responsible for driving the single-track sections. Their cutting wheels were designed so that, depending on the geology, the cutting knives for softer soils could be replaced with disc cutters for hard rock. For the tight curves in places, both machines have steering articulation.

Extensive additional equipment from Herrenknecht Group companies has contributed to optimized progress in the construction: navigation systems (VMT), rolling stock (MSD) and segment moulds (Herrenknecht Formwork).

After weekly top performances of up to 150 meters, in late November 2015 and mid-February 2016 the two 6.86 meter machines successfully completed their drives for Line 5. The final breakthrough of the large-diameter machine on June 20, 2016 completed the successfull mission of the Herrenknecht TBMs for Sao Paulo’s Metro Line 5.

Data Sheet

Country, Location

Brazil, São Paulo

Year

2013 – 2016

Application

Metro

Geology

Soft ground
Rock
Clay, silt, sand, granite

Tunnelling length

13,466 m

Machine Data

1x EPB Shield:
Diameter: 10,540 mm
Lining method: Segmental lining
Cutterhead power: 3,200 kW
Torque: 22,765 kNm

1x EPB Shield:
Diameter: 6,860 mm
Lining method: Segmental lining
Cutterhead power: 1,600 kW
Torque: 3,560 kNm

1x EPB Shield:
Diameter: 6,860 mm
Lining method: Segmental lining
Cutterhead power: 1,600 kW
Torque: 3,121 kNm

Your contact person Contact us

Steffen Dubé President and General Manager Herrenknecht Tunnelling Systems USA Inc.
Gerhard Goisser Commercial Manager Herrenknecht Tunnelling Systems USA, Inc.