Sungei Pandan River Crossing
Singapore
2007

In Singapore two cable tunnels had to be built crossing under a bay. The route is characterized by a simultenously vertical and horizontal curve (space curve). The use of soil conditioning agents permitted a secure advance through limestone, loam, fine sand and silt. To counteract the heavy wear on the discs in the heterogeneous geology, additional wear plates were welded onto the cutterhead.

Data Sheet

Country, Location

Singapore, Singapore

Year

2007

Application

Electricity

Geology

Limestone, loam, fine sand, silt

Tunnelling length

645 m

Machine Data

1x EPB Shield:
Diameter: 3,025 mm
Lining method: Pipe jacking
Cutterhead power: 250 kW
Torque: 820 kNm