No run of the mill mission on the Florida coast near Miami

In February 2016 construction company Bessac completed work on a protection tunnel in extremely difficult geology in South Florida. In just ten months and using a customized machine designed especially for the mission, a "Herrenknecht Combined Shield" (HCS, diameter 3.13 m), 1,613 meters were tunnelled adhering to the highest safety standards. A new sewer line was installed in the finished tunnel – after half a century in use the old pipe was simply worn out.

Additionally, the front area of the machine had to be accessible at all times during the challenge off Miami to allow for tool changes, for instance. For maximum safety a bulkhead with a dive pit was developed especially for the project. Thanks to the bulkhead between the front two machine parts and the overpressure thus enabled, muck and water cannot penetrate into the machine at the tunnel face. Should high water pressures nevertheless lead to flooding, the dive pit allows safe locking into the flooded area.

In the end the safety reserves were not needed. Neither the sophisticated lock system nor the EPB mode of the HCS machine were used. The ground was highly permeable as expected, however the proper design of the cutterhead and the appropriate disc cutters enabled the customer to perform only one maintenance stop, performed under compressed air after a novative ground treatment from the TBM.

"Dorsey" began the drive near the treatment plant on Virginia Key in April 2015. Right from the very first meter the project was characterized by its special requirements: to save space, with a diameter of twelve meters the launch shaft was rather small. At the beginning there was no room for the HSC machine's back-ups and they were only able to be used one by one after 70 meters of tunnelling. For the first section the TBM was therefore pushed forward in pipe jacking mode using a jacking frame adapter developed by the customer, the rest of the tunnel was then lined with concrete segments. At a depth of up to 21 meters below sea level, the 3.13 meter diameter "Dorsey" dug its way forward in the months that followed. After 227 working days came the breakthrough on Fisher Island on February 16, 2016 – top performances of up to 24 meters per day and about 300 meters per month confirmed the optimum configuration of the TBM. By the end of the year the new 60" discharge pipeline is due to be installed in the finished protection tunnel and put into operation. The successful drive on the Norris Cut project has pushed the boundaries of what is possible in Florida's tunnelling industry and contributed to its further development: "The project has set standards for work in Florida's underground and showed solutions for deep sewer lines in the porous Fort Thompson Formation," confirms Bernard Theron, President of Bessac.  With the construction of the Port Miami Tunnel already, machine technology from Herrenknecht had demonstrated that even the most complex ground conditions such as the Fort Thompson Formation can be safely mastered with optimally adapted technology. Despite its huge diameter of nearly 13 meters, in 2013 the EPB Shield S-600 reached its target reliably thanks to an additionally installed slurry circuit. According to internationally renowned accounting and consulting firm KPMG, in 2012 the Miami Port Tunnel was one of the ten most innovative transport projects in the world.
[Translate to English:]
[Translate to English:]

Your contact person Contact us

Steffen Dubé President and General Manager Herrenknecht Tunnelling Systems USA Inc.
Gerhard Goisser Commercial Manager Herrenknecht Tunnelling Systems USA, Inc.